An application of randomized minimum cut to the project time/cost tradeoff problem

作者:

Highlights:

摘要

In this paper, we introduce a solution procedure for solving the project time/cost tradeoff problem, such that a project’s duration is reduced for a specified amount of time at minimum cost. In our solution procedure, we find the minimum cut in the acyclic graph representing the critical paths of the project, using the fast algorithm of randomized minimum cut. The minimum cut so obtained, is then utilized to identify the project activities that are to be reduced, in order to achieve a certain reduction in the project’s total duration. The applicability of the proposed solution procedure is demonstrated by some test problems.

论文关键词:Project management,Randomized minimum cut

论文评审过程:Available online 1 July 2005.

论文官网地址:https://doi.org/10.1016/j.amc.2005.04.063