A hybrid simulation-optimization approach for the robust Discrete Time/Cost Trade-off Problem

作者:

Highlights:

摘要

We investigate a stochastic Discrete Time/Cost Trade-off Problem. This multimode project scheduling problem, requires assigning modes to activities, and scheduling the activities so that the sum of the activities cost and the expected tardiness cost is minimized. Furthermore, the derived solution should be stable. This stability property renders the schedule less sensitive to uncontrollable factors that may disrupt the project execution. To solve this problem, we propose a two-stage solution strategy. In the first stage, we implemented a simulation–optimization strategy that yields a cost-effective schedule. Next, a mixed-integer programming formulation is used to derive a schedule that is both stable and cost-effective. We report the results of computational experiments that attest to the efficacy of the proposed approach.

论文关键词:Multi-mode project scheduling,Discrete Time/Cost Trade-off Problem,Stochastic project scheduling,Simulation–optimization

论文评审过程:Available online 25 March 2015.

论文官网地址:https://doi.org/10.1016/j.amc.2015.02.092