A comparison of the performance of various project control methods using earned value management systems
作者:
Highlights:
• Two new project schedule control procedures using EVM are proposed: EVM-FPB and EVM-SNB.
• The effort spent by a project manager provides a functional distinction for the discussed project control approaches.
• The placement of control points in the project is inspired by critical chain/buffer management.
• Monte Carlo simulations are used to calculate tolerance limits for the control approaches and quantify their performance.
• The EVM-SNB approach is found to outperform the other project control approaches.
摘要
•Two new project schedule control procedures using EVM are proposed: EVM-FPB and EVM-SNB.•The effort spent by a project manager provides a functional distinction for the discussed project control approaches.•The placement of control points in the project is inspired by critical chain/buffer management.•Monte Carlo simulations are used to calculate tolerance limits for the control approaches and quantify their performance.•The EVM-SNB approach is found to outperform the other project control approaches.
论文关键词:Project management,Schedule control,Earned value management (EVM),Simulation
论文评审过程:Available online 11 December 2014.