Optimal integration of the facility location problem into the multi-project multi-supplier multi-resource Construction Supply Chain network design under the vendor managed inventory strategy
作者:
Highlights:
• A novel MILP is presented to the Construction Supply Chain (CSC) network design.
• Model integrates the facility location and the CSC network design problems.
• Model optimizes a CSC under vendor managed inventory strategy as an expert system.
• Model balances costs and increases cost controllability, in large CSC networks.
• Several novel theoretical contributions and managerial implications are derived.
摘要
•A novel MILP is presented to the Construction Supply Chain (CSC) network design.•Model integrates the facility location and the CSC network design problems.•Model optimizes a CSC under vendor managed inventory strategy as an expert system.•Model balances costs and increases cost controllability, in large CSC networks.•Several novel theoretical contributions and managerial implications are derived.
论文关键词:Construction Supply Chain,Optimization,Temporary facility location,Vendor managed inventory,Quantitative mathematical models,Expert systems
论文评审过程:Received 27 November 2018, Revised 22 July 2019, Accepted 24 July 2019, Available online 29 July 2019, Version of Record 3 August 2019.
论文官网地址:https://doi.org/10.1016/j.eswa.2019.112841